Total investment capital estimated at over VND3 trillion ($114.5 million).

The People’s Committee of Quang Tri province in Central Vietnam has approved the investment policy for two wind power projects with a combined investment capital of over VND3 trillion ($114.5 million).

The Phuc Thanh An Quang Tri and Phuc Thanh An Vinh Phuc projects have total capacity of 78 MW.

The Phuc Thanh An Quang Tri has a capacity of 48 MW, covering 16.8 ha, with investment capital estimated at VND1.703 trillion ($65 million).

Meanwhile, the Phuc Thanh An Vinh Phuc has a capacity of 30 MW, covering  an area of around 10.5 ha, with an estimated investment capital of VND1.278 trillion ($48.7 million).

Construction of the two projects is scheduled to start in the first quarter of 2026 and they are expected to be put into operation from the first quarter of 2027.

Source: Nguyễn Thuấn – vneconomy.vn